At Aqualytix, we understand the importance of working with organisations across the UK to ensure compliance. One of our valued customers is Severn Trent.
This case study explores how Aqualytix, in partnership with Severn Trent, transformed a complex and underperforming contract through collaborative leadership, operational innovation, and a relentless focus on performance improvement. What began as a fragmented and inconsistent service evolved into a model of efficiency, accountability, and forward-thinking practice.
The Background
The contract in question had experienced significant instability. Over a short period, several different Contract Performance Analysts (we’re proud to promote from within) had managed the account. This lack of continuity led to confusion, inconsistent expectations, and a general sense of disconnection between Severn Trent and Aqualytix.
However, not all hope was lost. When the current CPA took over, they quickly recognised that the contract was not in a healthy state by either party’s standards. The key performance indicators (KPIs) in place weren’t meaningful, and it became clear that some metrics were giving a false sense of performance.
Access to sites was another major issue. Many locations were remote and required multiple layers of approval and physical keys to enter. Technicians often arrived at sites only to find they couldn’t gain access due to outdated locks or missing keys. This not only delayed work but also demoralised the team.
So, we put our heads together and recognised the need for change.
Ben, the lead Business Development Manager, brought a strong background in operations and quickly became a key figure in driving improvements. Within just a few weeks, his impact was noticeable. He understood the challenges technicians faced and was proactive in supporting them, auditing their work, and ensuring they had what they needed to succeed.
Ben says: “Stepping into this role was both a challenge and an opportunity, and I was determined to make an immediate impact. Understanding the obstacles technicians face, I focused on proactive solutions—ensuring they had the resources and support necessary to excel. Improvements don’t happen overnight, but through collaboration and dedication, we’ve already seen tangible progress. This is just the beginning of a journey towards lasting change.”
Ben Hudson
One of the first major changes was the introduction of a weekly Work in Progress (WIP) call. These calls created a structured space to review all open jobs, discuss blockers, and track progress. This shift from reactive issue management to proactive performance tracking was a game-changer.
The team also began redesigning the SLA (Service Level Agreement) structure. The original 90-day SLA for job completion was far too long, especially for minor fixes. A new tiered system was proposed: urgent jobs to be completed within 24 hours, standard jobs within 10 days, and planned works within a month. This approach allowed for better prioritisation and faster response times.
Alison says: “Due to the new working relationship, we now have restored faith that reactive works will get completed, and we’re seeing more jobs being raised.”
Alison Shimeld
Results and Impact
The results of these changes were impressive. Each month, technicians were checking over 4,000 assets, with a 98% completion rate. The leadership team at Aqualytix and Alison’s collaborative working methods played a crucial role in supporting these changes.
The improvements made so far have laid a strong foundation for future success. The team is already considering publishing follow-up case studies to share their learnings with the wider industry. Even when certain trials don’t go as planned, the emphasis remains on learning, adapting, and continuously improving.
Looking Ahead
The team is now focused on evaluating the Fix-on-Fail trial and exploring opportunities to expand the model. There are also plans to upskill technicians, enabling them to handle a wider range of issues independently. This would reduce reliance on specialist contractors and further improve response times.
Conclusion
This case study demonstrates how a collaborative, data-informed, and people-first approach can transform contract performance. Through clear communication, operational innovation, and strong leadership, Severn Trent and Aqualytix have created a model of excellence that others in the industry can learn from. What began as a challenging situation has evolved into a story of resilience, innovation, and shared success.