Tight Deadlines, Tricky Access, No Disruption: How Aqualytix Delivered a Cold Water System Upgrade

How do you replace a failing 28,000 litre water tank perched on a fourth‑floor rooftop with only a loft hatch for access, and keep an entire school running without interruption? For Aqualytix, the answer was simple: you act fast, plan smart, and execute flawlessly.

The Problem 

The school’s cold water system relied on an ageing 28,000 litre storage tank that had deteriorated significantly. Only one section remained functional, and the cramped rooftop plantroom made routine maintenance increasingly unsafe. With the school also undergoing a major roof replacement, the tank’s condition became a pressing issue. It needed to be replaced quickly, safely, and without disrupting day-to-day operations. 

The Challenge 

Replacing the tank was never going to be straightforward. The plantroom sat on the fourth floor roof, accessible only through a loft hatch, meaning every piece of equipment had to be hoisted up. At the same time, the school needed continuous water supply, so a temporary system had to be installed before any removal work could begin. On top of this, the project had to be delivered within a very tight window to align with the wider construction programme. Any delay risked the school being unable to reopen on time. 

The Process 

Aqualytix moved quickly from the moment the enquiry arrived on 6 November 2025. A site survey was carried out the next day, followed by a detailed report on 10 November. To make sure the new tank would be efficient and fit for purpose, the team analysed two years of water usage data and agreed with the client that an 18,000 litre split division system would provide the best balance of capacity, turnover, and maintenance access. The order was confirmed on 26 November. 

Work began on 1 December, with tank panels and materials lifted to the roof. A temporary 3,000 litre tank was installed, cleaned, disinfected, and brought online the following evening, ensuring the school remained fully supplied throughout the programme. Once the temporary tank was up and running, the team dismantled the old 28,000 litre tank between 3 and 5 December and removed it safely from site. 

With the plantroom cleared, The new Purewater Storage Ltd Sectional tank was assembled between 8 and 10 December. The installation included completely upgraded valves, pipework, and improved layout to make future maintenance safer and more accessible. After full disinfection and chlorination, the new tank went live on 11 December. The temporary tank was removed on 12 December, and the system was checked again on 12 and 15 December to confirm everything was operating as expected.

The Outcome 

Despite complex logistics, limited access, and tight deadlines, the project was delivered safely, smoothly, and exactly on schedule. At no point did the school lose access to water, and the new installation now provides a modern, efficient, and fully compliant cold water storage solution. The redesigned layout allows for easier maintenance, better performance, and long term reliability. 

The school reopened as planned with a robust system in place, and the project stands as a strong example of Aqualytix’s ability to deliver high pressure, technically demanding works with confidence and care. It reflects the company’s commitment to preparation, expertise, and delivering results without compromise.